Calculator · Project economics

Solar LCOE calculator: levelised cost of electricity for a PV park

Solar LCOE calculator with the formula, benchmarked starting inputs and a Szolnok example: EUR 52/MWh at EUR 700/kWp, a 5% real discount rate and 30 years.

7 min read

Solar LCOE calculator

Capital cost
Fixed operating cost
Specific yield, year 1
Annual degradation
Lifetime
Discount rate (real)

Levelised cost of electricity

51.8 EUR/MWh

Share of capital cost in LCOE

74.0 %

Discounted lifetime energy

18,261 kWh/kWp

Sensitivity: LCOE in EUR/MWh

Discount rateCapex −20 % (EUR 560)Capex as set (EUR 700)Capex +20 % (EUR 840)
3.00 %37.843.849.9
5.00 %44.151.859.5
7.00 %51.160.670.0

Real terms, before tax. No inflation, financing structure, decommissioning or residual value. LCOE is a cost, not the market value of the electricity.

Key points

  1. Near Szolnok, Hungary, EUR 700/kWp capex, EUR 16/kWp per year opex, a 1,254 kWh/kWp PVGIS yield (2005 to 2023), 0.5%/year degradation, 30 years and a 5% real discount rate give a levelised cost of electricity of EUR 51.8/MWh, with capex 74.0% of discounted lifetime cost.
  2. For a park near Szolnok, Hungary (PVGIS, 2005 to 2023), raising the real discount rate from 5% to 8% lifts its levelised cost of electricity to EUR 65.2/MWh, because most of the cost is paid before the first kilowatt-hour.
  3. PVGIS (2005 to 2023 radiation data) gives 1,254 kWh/kWp a year for a fixed system at its optimum angles near Szolnok, Hungary, with its default 14% system loss, and 1,312 kWh/kWp with a 10% loss.
  4. Run with Fraunhofer ISE's own July 2024 inputs, the calculator's model reproduces its reported levelised cost of electricity range for ground-mounted PV in Germany, 4.1 to 6.9 EUR cents/kWh.
  5. IRENA puts the 2025 global weighted-average LCOE of utility-scale solar at USD 44/MWh, and Lazard's 2026 unsubsidised US range is USD 40 to 98/MWh.
  6. LCOE is a cost, not revenue: the right comparison is the price the park earns when it produces, not the market's average price.

The levelised cost of electricity (LCOE) of a solar park is its discounted lifetime cost divided by its discounted lifetime output. For a fixed-tilt park near Szolnok, with EUR 700/kWp capital cost, a 5% real discount rate and 30 years, the solar LCOE calculator above returns EUR 52/MWh. Capex is 74.0% of the discounted lifetime cost.

How is the LCOE of a solar park calculated?

To calculate LCOE, divide the present value of lifetime costs by the present value of lifetime energy. Costs are the up-front capital cost (capex) plus a fixed operating cost (opex) each year. Energy is the first-year yield, reduced by compound degradation each year. Both are discounted at the same real rate. In plain text, the levelised cost of electricity formula is:

LCOE = [ capex + SUM(t=1..N) opex / (1 + r)^t ]
       / [ SUM(t=1..N) yield × (1 - d)^(t - 1) / (1 + r)^t ]

N is the lifetime in years, r the real discount rate and d the annual degradation. Capex, opex and yield are per kWp (kilowatt-peak, direct current (DC) module capacity), so the raw result is in EUR/kWh. The calculator converts it to EUR/MWh. It has no tax, inflation, financing structure, decommissioning cost or residual value.

The outputs are the LCOE, capex's share of discounted lifetime cost (shown to one decimal, such as 74.0%), the discounted lifetime energy in kWh/kWp (the denominator of the formula) and a sensitivity table: discount rate plus and minus 2 points, capex plus and minus 20%.

What does each input do, and where do the starting values come from?

Capex is paid before any output, so it carries most of the result. Opex is paid every year. Yield sets how many MWh share the cost. Degradation and lifetime change the energy of later years, which is discounted most.

InputUnitStartBasis
Capital costEUR/kWp700Low end of the Fraunhofer Institute for Solar Energy Systems (ISE) range for German ground-mounted solar photovoltaic (PV) systems: EUR 700 to 900 (2024, excluding value-added tax). The Baden-Württemberg Centre for Solar Energy and Hydrogen Research (ZSW) assumes EUR 540 to 560 for 2026. The International Renewable Energy Agency (IRENA) reports USD 667/kW (DC) as the 2025 global average.
Fixed operating costEUR/kWp per year16ZSW: EUR 13 plus EUR 3 for direct marketing. Fraunhofer ISE: EUR 13.3.
Specific yield, year 1kWh/kWp1,254Run of the European Commission's Photovoltaic Geographical Information System (PVGIS) for Szolnok, below.
Degradation%/year0.5Fraunhofer ISE and ZSW: 0.25. The 2024 Annual Technology Baseline of the US National Renewable Energy Laboratory (NREL, now the National Laboratory of the Rockies): 0.7. See also the PV degradation calculator.
Lifetimeyears30Fraunhofer ISE: 30. Lazard: 35. ZSW: 20.
Discount rate (real)%/year5An input choice. Fraunhofer ISE: 3.5% for Germany. IRENA: about 3% to above 10%.

These are inputs, not measurements. Capex and the discount rate sit between German benchmarks and higher-risk cases. IRENA puts soft costs, such as permitting, grid connection and financing, at 26% of installed cost in Hungary, the highest of the countries compared (average 18%). It is a share, not a price, but it argues for testing higher capex.

Why does the discount rate matter so much for solar?

Most of a solar park's cost is paid before the first kilowatt-hour, while the output it buys arrives over decades. A higher rate shrinks discounted energy by more than discounted cost. IRENA calls renewables capital-intensive, with almost all lifetime cost incurred upfront. For a standardised, fully contracted project it puts the real weighted average cost of capital (WACC) near 3% in the United States and Australia. In the highest-risk economies it exceeds 10%.

In the default case, spreading EUR 700/kWp over 30 years costs EUR 35.7/kWp per year at 3% and EUR 62.2/kWp per year at 8%.

Input changedLCOE, EUR/MWhDifference from default
Discount rate 3%43.88.0 lower
Default (5%, EUR 700/kWp)51.8none
Discount rate 7%60.68.8 higher
Capex EUR 560/kWp44.17.7 lower
Capex EUR 840/kWp59.57.7 higher

A 2-point rise in the rate adds more than a 20% rise in capex. Lazard's sensitivity has the same shape: USD 53/MWh for average utility-scale solar at a 4.2% after-tax cost of capital, USD 83/MWh at 10.0%.

What specific yield should a fixed-tilt park near Szolnok use?

About 1,254 kWh/kWp in year 1. The run used PVGIS 5.3 through its API, with PVGIS-SARAH3 satellite radiation data (2005 to 2023) at 47.18 N, 20.19 E. It modelled crystalline silicon modules, a fixed array at the angles PVGIS optimises (38° tilt, azimuth 2° east of south) and the default 14% system loss. The capacity factor vs performance ratio explainer uses the same run.

Fixed system near SzolnokYield, kWh/kWp
Optimum angles, 14% loss (default)1,254
Same, PVGIS 2025 silicon coefficients1,295
Same as default, 10% loss1,312
25° tilt facing south, 14% loss1,228

The system loss covers everything between the modules and the grid, such as cables, inverters and dirt. PVGIS adds angle-of-incidence, spectral, temperature and irradiance effects. Total loss is 21.25%, which gives a performance ratio (PR) of 78.75% and a DC capacity factor of 14.3%.

The PVGIS manual lists ageing among the causes of the loss its 14% default covers. This calculator models degradation explicitly, so 14% with 0.5%/year probably counts some ageing twice, and the default yield is cautious. At a 10% loss the LCOE is 4.4% lower. The figure is a modelled multi-year average, with a year-to-year standard deviation of 49 kWh/kWp (3.9%).

What does a worked example look like?

Three cases from the formula above: the default, an 8% real discount rate (within IRENA's range) and the 10% system-loss yield.

DefaultDiscount rate 8%System loss 10%
Real discount rate, %585
Yield, year 1, kWh/kWp1,2541,2541,312
Discounted cost, EUR/kWp946.0880.1946.0
Discounted lifetime energy, kWh/kWp18,26113,49219,106
LCOE, EUR/MWh51.865.249.5
Capex share74.0%79.5%74.0%

In the default case, discounted cost is EUR 700 of capex plus EUR 246.0 of discounted opex. EUR 946.0 divided by 18,261 kWh is EUR 0.0518/kWh, or EUR 51.8/MWh. The 8% rate cuts discounted cost by 7% and discounted energy by 26%.

How does the result compare with published LCOE figures for solar in Europe and elsewhere?

The default of EUR 51.8/MWh sits inside the EUR 41 to 69/MWh that Fraunhofer ISE's German range implies. The sources differ in currency, price year, country and financing, so read them as context. No currency has been converted.

SourceScopeResultBasis
IRENA, 2026Utility-scale PV commissioned in 2025, global weighted averageUSD 44/MWh2025 USD. Excluding China 55. European average 59.
Fraunhofer ISE, July 2024Ground-mounted PV above 1 MWp, Germany4.1 to 5.0 EUR cents/kWh (south), 5.7 to 6.9 (north)Real 2024 values, 3.5% real WACC
Lazard, July 2026Utility-scale PV, United States, unsubsidisedUSD 40 to 98/MWh60% debt at 8%, 40% equity at 12%
This calculatorFixed tilt near SzolnokEUR 51.8/MWhReal, 5% discount rate

Given Fraunhofer ISE's own inputs, the model reproduces its study. Those are EUR 700 and 900/kWp, EUR 13.3/kWp per year, 0.25% degradation, 30 years, 3.5% real, and 1,280 kWh/kWp in southern and 935 kWh/kWp in northern Germany. The model returns EUR 41.3 and 50.1/MWh for the south and EUR 56.6 and 68.6/MWh for the north, against the study's 4.1, 5.0, 5.7 and 6.9 EUR cents/kWh.

At the same capex, the default is EUR 10.5/MWh above the study's low end of EUR 41.3/MWh. Changing inputs one at a time, the 5% discount rate adds EUR 5.9 of that, higher opex EUR 2.2, faster degradation EUR 1.2 and Szolnok's 2% lower yield EUR 0.9.

How does LCOE differ from market value?

LCOE is a cost per MWh averaged over all output, not revenue. In LCOE vs market value, the right comparison is the price the park earns when it produces, not the market's average price. The study of negative quarter-hours in Hungary's first year of 15-minute day-ahead prices covers when midday prices fall below zero.

What this means for owners, investors and analysts

  • Owners and developers: test capex and the discount rate first, then compare the result with the price the park earns when it produces.
  • Investors and lenders: treat LCOE as a screening number and match the discount rate to the revenue risk.
  • Analysts: compare LCOE figures only with the same currency, price year, country and cost of capital.

Limits of the calculator

  • No tax, inflation, financing structure, decommissioning cost or residual value. One real discount rate stands in for the whole cost of capital.
  • Yield falls by the same percentage every year, with no first-year step, outage or curtailment.
  • Capex and yield must share a basis. The starting values use kWp (DC); capex per kW of alternating current (AC) needs a yield per kW of AC.
  • The starting values come from German, global and US sources, not Hungarian market quotes. PVGIS gives a modelled multi-year average, not a site energy yield assessment.
  • The output is an estimate. Data sourcing is described on the methods page.

What is a typical LCOE for solar in Europe?

IRENA reports a European average of USD 59/MWh for utility-scale solar commissioned in 2025. Fraunhofer ISE's 2024 study gives 4.1 to 6.9 EUR cents/kWh for German ground-mounted parks, depending on sunshine and capex. Currency, year and cost of capital differ, so the figures are not interchangeable.

Should the discount rate be real or nominal?

This calculator uses a real rate with costs and yields in constant prices, so it models no inflation. A nominal rate needs nominal cash flows, with opex escalated by inflation. Fraunhofer ISE warns that mixing real and nominal values is incorrect.

Why does PVGIS use a 14% system loss?

PVGIS applies 14% by default for losses between the modules and the grid, such as cables, inverters and dirt. Its manual also lists module ageing among the causes. This calculator models degradation separately, so a lower system loss is reasonable when design data exists.

Is the lowest LCOE always the best solar project?

No. LCOE measures cost per MWh, not revenue. The right comparison is the price the park earns when it produces, so a low LCOE does not by itself show a good project.

Does the calculator include tax, financing or decommissioning?

No. It has no tax, inflation, financing structure, decommissioning cost or residual value. The single real discount rate stands in for the cost of capital.
  1. Renewable power generation costs in 2025, IRENA, 2026-07
  2. Levelized cost of electricity: renewable energy technologies (July 2024 edition), Fraunhofer ISE, 2024-07
  3. Levelized Cost of Energy+ 2026 (LCOE version 19.0), Lazard, 2026-07-13
  4. PVGIS user manual, European Commission, Joint Research Centre
  5. PVGIS API non-interactive service, European Commission, Joint Research Centre
  6. Stromgestehungskosten von Photovoltaikanlagen des ersten Segments (Freiflächenanlagen), ZSW for the German Federal Ministry for Economic Affairs and Climate Action, 2024-10
  7. Utility-scale PV, 2024 Annual Technology Baseline, NREL (now the National Laboratory of the Rockies), 2024

Results are estimates from a simplified model. They are not engineering, investment or financial advice. How this site works with data: methods and sources.